Home > Case Studies > Industrial & Manufacturing > Ford Motor Company
Ford Motor Company – Automotive Component Holdings – Ypsilanti Demolition
Adamo demolished Building 1, the Powerhouse, the Oil House and decommissioned and removed fuel tanks at the former Automotive Component Holdings Ypsilanti Plant for Ford Land. The project site is located on Ford Lake in Ypsilanti, Michigan.
During the course of the demolition project, subsurface contamination was discovered which posed a threat to the adjacent waterway. Over 50,000 cubic yards of contaminated concrete and soil were excavated and disposed of and engineering controls put in place to protect the surrounding environment.